Re: [PATCH v3 net 0/4] qbv cycle time extension/truncation

From: Eric Dumazet
Date: Tue Dec 19 2023 - 12:10:57 EST


On Tue, Dec 19, 2023 at 9:17 AM Faizal Rahim
<faizal.abdul.rahim@xxxxxxxxxxxxxxx> wrote:
>
> According to IEEE Std. 802.1Q-2018 section Q.5 CycleTimeExtension,
> the Cycle Time Extension variable allows this extension of the last old
> cycle to be done in a defined way. If the last complete old cycle would
> normally end less than OperCycleTimeExtension nanoseconds before the new
> base time, then the last complete cycle before AdminBaseTime is reached
> is extended so that it ends at AdminBaseTime.
>

Hmm... Is this series fixing any of the pending syzbot bugs ?