On 7/15/23 22:14, Tree Davies wrote:
Philipp,

I think I understand what I did wrong. Each of these original patches were
created/based from the same commit hash. So it makes sense that only the
first one applied would apply cleanly and the others would fail.

My apologies,
Tree

Hi Tree,

you could work this way if you ensure that each patch does not modify code (and some lines above and below) a previous patch modified. But it is not a good way to do so. Existing tools assume that you create your commits onto each other and then make patches out of them.

Another issue right now is that approximately 18 patches send in and are possibly applied (for rtl8192e). Your patches need to fit onto those patches. Otherwise they cannot be applied and will be rejected.

Typically Greg applies all patches once a week. But it seems that he has a bunch of other more urgent tasks. So you need to focus on other kernel related task like educate yourself or prepare patches without sending them in.

Thanks for your support.

Bye Philipp